Minimum order quantity
Our current minimum for standard private label gummy formats is 5,000 bottles. Production runs carry fixed work — line cleaning, formula setup, mold configuration and QC sampling — regardless of whether the order is 5,000 or 50,000 bottles. Below a certain volume, those fixed costs make the unit economics difficult.
A few things worth understanding about MOQ:
- MOQ is usually stated in bottles, not gummies. 5,000 bottles at 60 count is 300,000 gummies. Confirm which unit a quote refers to before comparing suppliers.
- Custom molds raise the floor. A custom gummy shape requires tooling, and tooling amortises across the run. Standard shapes carry no such cost.
- Reorder terms can differ. Ask whether the supplier can combine packaging buys, reserve raw materials or schedule repeat runs against a forecast.
Lead times
| Stage | Typical duration |
| Feasibility review | Days — before any quote is issued |
| Sample development | 7–14 days |
| Your evaluation | Yours to control — usually the longest stage in practice |
| Pilot validation | Added for high-load or novel formulas |
| Production | Current planning range: 7–15 days after sample approval and material readiness |
| International freight | Quoted separately; route, service level, port conditions and customs all affect timing |
The number most brands underestimate is their own evaluation stage. Samples arrive, and then they sit while the team debates flavour. Building a decision deadline into your own calendar before samples ship is the single easiest way to compress a launch timeline.
Freight is the other large block. Confirm the Incoterm, importer-of-record responsibility, estimated transit time and customs-document package before you compare total launch timelines.
The five things that actually move unit cost
1. Active load
By a wide margin the biggest driver. A gummy carrying 5 g of creatine contains vastly more raw material than one carrying 25 mcg of vitamin D3, and high-load formulas also run slower and reject more. Doubling your dose does not double your cost, but it moves it more than any other single decision.
2. Which form of the active
Magnesium glycinate costs considerably more per milligram of elemental magnesium than magnesium oxide, and occupies more mass. Choosing glycinate for a cleaner taste profile is a legitimate decision — but it is a cost decision as much as a formulation one, and it should be made deliberately.
3. Order quantity
Fixed setup costs spread across the run. The step between 5,000 and 20,000 bottles is usually the most dramatic per-unit improvement you will see; gains flatten after that.
4. Packaging
Frequently underestimated. Bottle type, closure, label stock, shrink band, carton and insert all add up, and for lower-dose products packaging can approach the cost of what goes inside it. Opaque containers — which we recommend for light-sensitive actives like CoQ10 — cost more than clear PET.
5. Certifications and testing scope
Organic, Halal, Kosher and Non-GMO certification each add cost and often restrict ingredient sourcing. Testing scope is similar: a basic potency panel is inexpensive, while a full heavy metals, microbiological and stability program across multiple timepoints is not. Neither is optional if your channel requires it — but both should be scoped deliberately rather than discovered late.
Why manufacturers hesitate to quote immediately
A quote given before feasibility review is a guess, and guesses in this category tend to be optimistic. The specification that determines your price — active load, form, piece weight, count, packaging, testing — is exactly the specification that determines whether the product can be manufactured consistently at all.
An immediate quote against an incomplete brief is a mild warning sign. It usually means either the number will move later, or that feasibility is being treated as your problem rather than the manufacturer's.
What to have ready before you make contact
You will get a faster and more accurate response if you can state:
- Target active and dose per serving
- Preferred serving size — how many gummies a consumer takes
- Sugar system: sugared, sugar-free, or reduced sugar
- Base preference: pectin (vegetarian) or gelatin
- Packaging format and count per container
- First order quantity and target launch date
- Any certification your sales channel requires
If some of those are still open, say so — an experienced manufacturer will have opinions, and the conversation is more useful than a quote against assumptions nobody stated.
Our current specification, MOQ and lead times are listed on the capability page.